Update - Maynooth Education Campus Building Works

18-April-19

Please see below an updated timeline received from the ETB today.

MAYNOOTH CAMPUS UPDATE

The key dates for the next stages of the project were forwarded by KWETB today.

Tender Issue – 17th April 2019

Site visits for all tendering contractors – 29th & 30th April

Tender Return – 22nd May 2019

Tender Report- 5th June 2019

DoES Review – 12th June 2019 (1 week)

Letter of Intent – 12th June 2019

Alcatel period – unsuccessful contractors 13th June – 28th June 2019 (16 days)

Response to Letter of Intent – 19th June 2019 (7 days)

Supplementary Tender Report – 21st June 2019

DoES Review – 28th June 2019 (1 week)

Letter of Acceptance – 28th June

Phase 1 completion – School Buildings 1 & 2 and Site works – 10 months – 1st May 2020

Phase 2 Completion – Sports Facility – 29th June 2020

The envelope works are nearing completion the required programme to fitout the schools has reduced to 10 months .